<law><site_title>Virginia Decoded</site_title><site_url>https://vacode.org</site_url><law_id>68074</law_id><section_number>56-585.1:14</section_number><catch_line>(Effective until December 31, 2029) Recovery of development costs associated with small modular reactor</catch_line><edition url="https://vacode.org/2025/" slug="2025" current="TRUE" last_updated="">2025</edition><structure><unit label="title" level="1" order_by="1" identifier="56">Public Service Companies</unit><unit label="chapter" level="2" order_by="1" identifier="23">Virginia Electric Utility Regulation Act</unit></structure><text>
						<section id="A"><p><span class="prefix-number">A.</span> As used in this section:
			&#x201C;<span class="dictionary">Small modular reactor</span>&#x201D; or &#x201C;SMR&#x201D; means a nuclear reactor that produces nuclear power and has a nameplate capacity that does not exceed 500 megawatts of generating capacity per reactor.
			&#x201C;<span class="dictionary">SMR facility</span>&#x201D; means an SMR or multiple <span class="dictionary">SMRs</span> that generate electricity at a single site.
			&#x201C;<span class="dictionary">SMR project development costs</span>&#x201D; or &#x201C;<span class="dictionary">project costs</span>&#x201D; means all costs associated with the development of one or more <span class="dictionary">SMRs</span>, including costs of evaluation, design, engineering, federal approvals and licensing, environmental analysis and permitting, early site permitting, equipment procurement, and authorized <span class="dictionary">rate</span> of return.
			&#x201C;<span class="dictionary">Utility</span>&#x201D; means a Phase II <span class="dictionary">Utility</span>, as that term is defined in subdivision A 1 of &#xA7; <a class="law" title="Generation, distribution, and transmission rates after capped rates terminate or expire" href="/56-585.1/">56-585.1</a>. <a id="paragraph-246465" class="section-permalink" href="https://vacode.org/56-585.1_14/#A"><i class="fa fa-link"/></a></p></section>
						<section id="B"><p><span class="prefix-number">B.</span> Notwithstanding any limitation under subdivision A 6 of &#xA7; <a class="law" title="Generation, distribution, and transmission rates after capped rates terminate or expire" href="/56-585.1/">56-585.1</a>, the <span class="dictionary">utility</span> may <span class="dictionary">petition</span> the <span class="dictionary">Commission</span> at any time for approval of a <span class="dictionary">rate</span> adjustment clause pursuant to subdivision A 6 of &#xA7; <a class="law" title="Generation, distribution, and transmission rates after capped rates terminate or expire" href="/56-585.1/">56-585.1</a> for the recovery of <span class="dictionary">SMR project development costs</span>. The <span class="dictionary">utility</span> may <span class="dictionary">petition</span> the <span class="dictionary">Commission</span> for up to one <span class="dictionary">SMR facility</span> pursuant to this section. Such utilities may <span class="dictionary">petition</span> the <span class="dictionary">Commission</span> for SMR project development cost recovery along separate development phases and, if the <span class="dictionary">Commission</span> determines such projected or actual <span class="dictionary">project costs</span> to be reasonable and prudent, such <span class="dictionary">project costs</span> may be recovered by such <span class="dictionary">utility</span> on a timely and current basis from customers prior to any approval pursuant to subsection D of &#xA7; <a class="law" title="Transmission and distribution of electric energy" href="/56-580/">56-580</a> or the commercial operation date of any such <span class="dictionary">SMR facility</span>. Any <span class="dictionary">SMR project development costs</span> incurred prior to July 1, 2024, and 20 percent of <span class="dictionary">SMR project development costs</span> incurred after July 1, 2024, shall not be eligible for accelerated cost recovery pursuant to this section and may be recovered through the <span class="dictionary">utility</span>&#x2019;s <span class="dictionary">rates</span> for generation and distribution services pursuant to subdivision A 1 of &#xA7; <a class="law" title="Generation, distribution, and transmission rates after capped rates terminate or expire" href="/56-585.1/">56-585.1</a>. The <span class="dictionary">utility</span> that <span class="dictionary">petitions</span> the <span class="dictionary">Commission</span> for recovery of <span class="dictionary">SMR project development costs</span> shall demonstrate that such <span class="dictionary">utility</span> has evaluated funding opportunities from the U.S. Department of Energy. Nothing in this section shall limit the <span class="dictionary">Commission</span>&#x2019;s discretion to determine whether the proposed <span class="dictionary">SMR project development costs</span> are reasonable and prudent. As part of a <span class="dictionary">final order</span> approving such cost recovery, the <span class="dictionary">Commission</span> may impose a deadline by which the relevant <span class="dictionary">utility</span> shall either (i) place an SMR into commercial operation or (ii) sell the permitted site, unless it is at a previously existing nuclear site, and return the proceeds of the sale to customers. The length of such deadline shall be at the <span class="dictionary">Commission</span>&#x2019;s discretion; however, it shall provide the <span class="dictionary">utility</span> a reasonable timeframe in which to obtain all necessary permits and approvals, including allowing for approval by federal agencies such as the Nuclear Regulatory <span class="dictionary">Commission</span>, and completing construction of an SMR. <a id="paragraph-246466" class="section-permalink" href="https://vacode.org/56-585.1_14/#B"><i class="fa fa-link"/></a></p></section>
						<section id="C"><p><span class="prefix-number">C.</span> Nothing in this section shall limit the <span class="dictionary">Commission</span>&#x2019;s authority to approve or deny a <span class="dictionary">petition</span> for recovery of <span class="dictionary">SMR project development costs</span> or to require a <span class="dictionary">utility</span> to demonstrate that such <span class="dictionary">utility</span> made reasonable good-faith efforts to secure appropriate funding opportunities from the U.S. Department of Energy. The annual revenue requirement for any <span class="dictionary">rate</span> adjustment clause authorized pursuant to this section shall not exceed an amount that would increase the monthly bill of the <span class="dictionary">utility</span>&#x2019;s typical Virginia residential customer, utilizing 1,000 kilowatt hours of electricity monthly, by more than $1.40. <a id="paragraph-246467" class="section-permalink" href="https://vacode.org/56-585.1_14/#C"><i class="fa fa-link"/></a></p></section></text><history>2024, c. 789.</history><metadata></metadata></law>