<?xml version="1.0"?>
<law><site_title>Virginia Decoded</site_title><site_url>https://vacode.org</site_url><law_id>86919</law_id><section_number>56-585.1:15</section_number><catch_line>(Effective until July 1, 2034) Recovery of development costs associated with small modular nuclear facility</catch_line><edition url="https://vacode.org/2025/" slug="2025" current="TRUE" last_updated="">2025</edition><referred_to_by><reference>56-596.5</reference></referred_to_by><structure><unit label="title" level="1" order_by="1" identifier="56">Public Service Companies</unit><unit label="chapter" level="2" order_by="1" identifier="23">Virginia Electric Utility Regulation Act</unit></structure><text>
						<section id="A"><p><span class="prefix-number">A.</span> As used in this section:
			&#x201C;<span class="dictionary">Phase I Utility</span>&#x201D; means an investor-owned <span class="dictionary">incumbent electric utility</span> that was, as of July 1, 1999, not bound by a <span class="dictionary">rate</span> case <span class="dictionary">settlement</span> adopted by the <span class="dictionary">Commission</span> that extended its application beyond January 1, 2002.
			&#x201C;<span class="dictionary">Project development costs</span>&#x201D; means all capital and operation and maintenance costs associated with a potential <span class="dictionary">small modular nuclear facility</span> incurred by a <span class="dictionary">Phase I Utility</span> before issuance of a certificate for a <span class="dictionary">small modular nuclear facility</span> located in the Commonwealth, including the costs of evaluation, design, engineering, environmental analysis and permitting, land options or acquisition, and early site permitting, as that term is defined in 10 C.F.R. &#xA7; 52.1. &#x201C;<span class="dictionary">Project development costs</span>&#x201D; does not include the costs to obtain construction permits, combined licensing costs required by the Nuclear Regulatory <span class="dictionary">Commission</span>, or construction costs other than construction costs necessary for early site permitting.
			&#x201C;<span class="dictionary">Small modular nuclear facility</span>&#x201D; means a nuclear reactor that has a rated electric generating capacity of not more than 500 megawatts that is capable of being constructed and operated either alone or in combination with one or more similar reactors at a single site. <a id="paragraph-311206" class="section-permalink" href="https://vacode.org/56-585.1_15/#A"><i class="fa fa-link"/></a></p></section>
						<section id="B"><p><span class="prefix-number">B.</span> Prior to the filing of an application for a certificate to construct a <span class="dictionary">small modular nuclear facility</span> to serve customers in the Commonwealth or in West Virginia and no earlier than July 1, 2024, a <span class="dictionary">Phase I Utility</span> may request the <span class="dictionary">Commission</span> to review the <span class="dictionary">Phase I Utility</span>&#x2019;s decision to incur <span class="dictionary">project development costs</span>. The <span class="dictionary">Commission</span> shall hold a <span class="dictionary">hearing</span> regarding the request and shall <span class="dictionary">issue</span> a <span class="dictionary">final order</span> within 180 days after the date on which the <span class="dictionary">Phase I Utility</span> files its request. <a id="paragraph-311207" class="section-permalink" href="https://vacode.org/56-585.1_15/#B"><i class="fa fa-link"/></a></p></section>
						<section id="C"><p><span class="prefix-number">C.</span> All approved reasonable and prudent <span class="dictionary">project development costs</span> incurred for a potential <span class="dictionary">small modular nuclear facility</span> shall be recovered through a <span class="dictionary">rate</span> adjustment clause filed pursuant to subdivision A 6 of &#xA7; <a class="law" title="Generation, distribution, and transmission rates after capped rates terminate or expire" href="/56-585.1/">56-585.1</a>, amortized over a period equal to the period during which the costs were incurred or five years, whichever is greater. Beginning July 1, 2025, a <span class="dictionary">Phase I Utility</span> may make annual filings pursuant to subdivision A 6 of &#xA7; <a class="law" title="Generation, distribution, and transmission rates after capped rates terminate or expire" href="/56-585.1/">56-585.1</a> to recover <span class="dictionary">project development costs</span> incurred for a <span class="dictionary">small modular nuclear facility</span>, provided that the annual revenue requirement shall not exceed $25 million and that the overall <span class="dictionary">project development costs</span> recovered in such <span class="dictionary">rate</span> adjustment clause shall not exceed $125 million, excluding the cost of acquiring a site. Any such <span class="dictionary">rate</span> adjustment clause shall not be implemented prior to January 1, 2026. <a id="paragraph-311208" class="section-permalink" href="https://vacode.org/56-585.1_15/#C"><i class="fa fa-link"/></a></p></section>
						<section id="D"><p><span class="prefix-number">D.</span> A <span class="dictionary">Phase I Utility</span> may only request for review under subsection B <span class="dictionary">project development costs</span> that are (i) associated with the preliminary analysis, testing, and evaluation of a site related to the property to be owned by such <span class="dictionary">Phase I Utility</span>, (ii) associated with the purchase of property to be owned by such <span class="dictionary">Phase I Utility</span>, or (iii) related to siting work on property owned by such <span class="dictionary">Phase I Utility</span>. <a id="paragraph-311209" class="section-permalink" href="https://vacode.org/56-585.1_15/#D"><i class="fa fa-link"/></a></p></section>
						<section id="E"><p><span class="prefix-number">E.</span> If a <span class="dictionary">Phase I Utility</span> serves customers in more than one <span class="dictionary">jurisdiction</span>, the percentage of <span class="dictionary">project development costs</span> to be recovered shall be equal to the percentage of associated energy and capacity from the <span class="dictionary">small modular nuclear facility</span> that is assigned to serve customers located in the Commonwealth. <a id="paragraph-311210" class="section-permalink" href="https://vacode.org/56-585.1_15/#E"><i class="fa fa-link"/></a></p></section>
						<section id="F"><p><span class="prefix-number">F.</span> As part of a <span class="dictionary">final order</span> approving cost recovery pursuant to this section, the <span class="dictionary">Commission</span> may impose a deadline by which the <span class="dictionary">Phase I Utility</span> shall either (i) place a <span class="dictionary">small modular nuclear facility</span> into commercial operation or (ii) sell the permitted site and return the proceeds of the sale to customers. The length of such deadline shall be at the <span class="dictionary">Commission</span>&#x2019;s discretion; however, it shall provide the utility a reasonable timeframe in which to obtain all necessary permits and approvals, including allowing for approval by federal agencies such as the Nuclear Regulatory <span class="dictionary">Commission</span>, and completing construction of a <span class="dictionary">small modular nuclear facility</span>. <a id="paragraph-311211" class="section-permalink" href="https://vacode.org/56-585.1_15/#F"><i class="fa fa-link"/></a></p></section></text><history>2024, c. 836.</history><metadata></metadata></law>