<law><site_title>Virginia Decoded</site_title><site_url>https://vacode.org</site_url><law_id>78424</law_id><section_number>56-594.2</section_number><catch_line>Small agricultural generators</catch_line><edition url="https://vacode.org/2025/" slug="2025" current="TRUE" last_updated="">2025</edition><referred_to_by><reference>15.2-2232</reference><reference>15.2-2288.7</reference><reference>15.2-2316.6</reference><reference>56-585.1:8</reference><reference>56-594</reference><reference>58.1-2636</reference></referred_to_by><structure><unit label="title" level="1" order_by="1" identifier="56">Public Service Companies</unit><unit label="chapter" level="2" order_by="1" identifier="23">Virginia Electric Utility Regulation Act</unit></structure><text>
						<section id="A"><p><span class="prefix-number">A.</span> As used in this section:
			&#x201C;<span class="dictionary">Small agricultural generating facility</span>&#x201D; means an electrical generating facility that: <a id="paragraph-281060" class="section-permalink" href="https://vacode.org/56-594.2/#A"><i class="fa fa-link"/></a></p></section>
						<section id="A1" class="indent-1"><p><span class="prefix-number">1.</span> Has a capacity:
				a. Of not more than 1.5 megawatts; and
				b. That does not exceed 150 percent of the customer&#x2019;s expected annual energy consumption based on the previous 12 months of billing history or an annualized calculation of billing history if 12 months of billing history is not available; <a id="paragraph-281061" class="section-permalink" href="https://vacode.org/56-594.2/#A1"><i class="fa fa-link"/></a></p></section>
						<section id="A2" class="indent-1"><p><span class="prefix-number">2.</span> Uses as its total source of fuel <span class="dictionary">renewable energy</span>; <a id="paragraph-281062" class="section-permalink" href="https://vacode.org/56-594.2/#A2"><i class="fa fa-link"/></a></p></section>
						<section id="A3" class="indent-1"><p><span class="prefix-number">3.</span> Is located on the customer&#x2019;s premises and is interconnected with its <span class="dictionary">utility</span> through a separate meter; <a id="paragraph-281063" class="section-permalink" href="https://vacode.org/56-594.2/#A3"><i class="fa fa-link"/></a></p></section>
						<section id="A4" class="indent-1"><p><span class="prefix-number">4.</span> Is interconnected and operated in parallel with an <span class="dictionary">electric utility</span>&#x2019;s distribution but not transmission facilities; <a id="paragraph-281064" class="section-permalink" href="https://vacode.org/56-594.2/#A4"><i class="fa fa-link"/></a></p></section>
						<section id="A5" class="indent-1"><p><span class="prefix-number">5.</span> Is designed so that the electricity generated by the facility is expected to remain on the utility&#x2019;s distribution system; and <a id="paragraph-281065" class="section-permalink" href="https://vacode.org/56-594.2/#A5"><i class="fa fa-link"/></a></p></section>
						<section id="A6" class="indent-1"><p><span class="prefix-number">6.</span> Is a qualifying small power production facility pursuant to the Public Utility Regulatory Policies Act of 1978 (P.L. 95-617).
				&#x201C;<span class="dictionary">Small agricultural generator</span>&#x201D; means a customer that: <a id="paragraph-281066" class="section-permalink" href="https://vacode.org/56-594.2/#A6"><i class="fa fa-link"/></a></p></section>
						<section id="A1" class="indent-1"><p><span class="prefix-number">1.</span> Is not an eligible agricultural customer-generator pursuant to &#xA7; <a class="law" title="Net energy metering provisions" href="/56-594/">56-594</a>; <a id="paragraph-281067" class="section-permalink" href="https://vacode.org/56-594.2/#A1"><i class="fa fa-link"/></a></p></section>
						<section id="A2" class="indent-1"><p><span class="prefix-number">2.</span> Operates a <span class="dictionary">small agricultural generating facility</span> as part of (i) an agricultural business or (ii) any business granted a manufacturer license pursuant to subdivisions 1 through 6 of &#xA7; <a class="law" title="Manufacturer licenses" href="/4.1-206.1/">4.1-206.1</a>; <a id="paragraph-281068" class="section-permalink" href="https://vacode.org/56-594.2/#A2"><i class="fa fa-link"/></a></p></section>
						<section id="A3" class="indent-1"><p><span class="prefix-number">3.</span> May be served by multiple meters that are located at separate but contiguous sites; <a id="paragraph-281069" class="section-permalink" href="https://vacode.org/56-594.2/#A3"><i class="fa fa-link"/></a></p></section>
						<section id="A4" class="indent-1"><p><span class="prefix-number">4.</span> May aggregate the electricity consumption measured by the meters, solely for purposes of calculating 150 percent of the customer&#x2019;s expected annual energy consumption, but not for billing or retail service purposes, provided that the same utility serves all of its meters; <a id="paragraph-281070" class="section-permalink" href="https://vacode.org/56-594.2/#A4"><i class="fa fa-link"/></a></p></section>
						<section id="A5" class="indent-1"><p><span class="prefix-number">5.</span> Uses not more than 25 percent of contiguous land owned or controlled by the agricultural business for purposes of the <span class="dictionary">renewable energy</span> generating facility; and <a id="paragraph-281071" class="section-permalink" href="https://vacode.org/56-594.2/#A5"><i class="fa fa-link"/></a></p></section>
						<section id="A6" class="indent-1"><p><span class="prefix-number">6.</span> <span class="dictionary">Issues</span> a certification under <span class="dictionary">oath</span> as to the amount of land being used for renewable generation.
				&#x201C;Utility&#x201D; includes <span class="dictionary">supplier</span> or <span class="dictionary">distributor</span>, as applicable. <a id="paragraph-281072" class="section-permalink" href="https://vacode.org/56-594.2/#A6"><i class="fa fa-link"/></a></p></section>
						<section id="B"><p><span class="prefix-number">B.</span> A <span class="dictionary">small agricultural generator</span> electing to interconnect pursuant to this section shall: <a id="paragraph-281073" class="section-permalink" href="https://vacode.org/56-594.2/#B"><i class="fa fa-link"/></a></p></section>
						<section id="B1" class="indent-1"><p><span class="prefix-number">1.</span> Enter into a power purchase agreement with its utility to sell all of the electricity generated from its <span class="dictionary">small agricultural generating facility</span>, which power purchase agreement obligates the utility to purchase all the electricity generated, at a <span class="dictionary">rate</span> agreed upon by the parties, but at a <span class="dictionary">rate</span> not less than the utility&#x2019;s <span class="dictionary">Commission</span>-approved avoided cost tariff for energy and capacity; <a id="paragraph-281074" class="section-permalink" href="https://vacode.org/56-594.2/#B1"><i class="fa fa-link"/></a></p></section>
						<section id="B2" class="indent-1"><p><span class="prefix-number">2.</span> Have the rights described in subsection E of &#xA7; <a class="law" title="Net energy metering provisions" href="/56-594/">56-594</a> pertaining to an eligible agricultural customer-generator as to the <span class="dictionary">renewable energy</span> certificates or other environmental attributes generated by the <span class="dictionary">renewable energy</span> generating facility; <a id="paragraph-281075" class="section-permalink" href="https://vacode.org/56-594.2/#B2"><i class="fa fa-link"/></a></p></section>
						<section id="B3" class="indent-1"><p><span class="prefix-number">3.</span> Abide by the appropriate small generator interconnection process as described in 20VAC5-314; and <a id="paragraph-281076" class="section-permalink" href="https://vacode.org/56-594.2/#B3"><i class="fa fa-link"/></a></p></section>
						<section id="B4" class="indent-1"><p><span class="prefix-number">4.</span> Pay to its utility any necessary additional expenses as required by this section. <a id="paragraph-281077" class="section-permalink" href="https://vacode.org/56-594.2/#B4"><i class="fa fa-link"/></a></p></section>
						<section id="C"><p><span class="prefix-number">C.</span> Utilities: <a id="paragraph-281078" class="section-permalink" href="https://vacode.org/56-594.2/#C"><i class="fa fa-link"/></a></p></section>
						<section id="C1" class="indent-1"><p><span class="prefix-number">1.</span> Shall purchase, through the power purchase agreement described in subdivision B 1, all of the output of the <span class="dictionary">small agricultural generator</span>; <a id="paragraph-281079" class="section-permalink" href="https://vacode.org/56-594.2/#C1"><i class="fa fa-link"/></a></p></section>
						<section id="C2" class="indent-1"><p><span class="prefix-number">2.</span> Shall recover the cost for its distribution facilities to the generating meter either through a proportional cost-sharing agreement with the <span class="dictionary">small agricultural generator</span> or through metering the total capacity and energy placed on the distribution system by the <span class="dictionary">small agricultural generator</span>; <a id="paragraph-281080" class="section-permalink" href="https://vacode.org/56-594.2/#C2"><i class="fa fa-link"/></a></p></section>
						<section id="C3" class="indent-1"><p><span class="prefix-number">3.</span> Shall recover all costs incurred by the utility to purchase electricity, capacity, and <span class="dictionary">renewable energy</span> certificates from the <span class="dictionary">small agricultural generator</span>:
				a. If the utility has a <span class="dictionary">Commission</span>-approved <span class="dictionary">Renewable Energy</span> Portfolio Standard (RPS) plan and <span class="dictionary">rate</span> adjustment clause, through the utility&#x2019;s RPS <span class="dictionary">rate</span> adjustment clause; or
				b. If the utility does not have a <span class="dictionary">Commission</span>-approved RPS <span class="dictionary">rate</span> adjustment clause, through the utility&#x2019;s fuel adjustment clause or through the utility&#x2019;s cost of purchased power; <a id="paragraph-281081" class="section-permalink" href="https://vacode.org/56-594.2/#C3"><i class="fa fa-link"/></a></p></section>
						<section id="C4" class="indent-1"><p><span class="prefix-number">4.</span> May conduct <span class="dictionary">settlement</span> transactions for purchased power in dollars on the <span class="dictionary">small agricultural generator</span>&#x2019;s electric bill or through other means of <span class="dictionary">settlement</span>, in the utility&#x2019;s sole discretion; <a id="paragraph-281082" class="section-permalink" href="https://vacode.org/56-594.2/#C4"><i class="fa fa-link"/></a></p></section>
						<section id="C5" class="indent-1"><p><span class="prefix-number">5.</span> Shall bill the <span class="dictionary">small agricultural generator</span> eligible costs for small generator interconnection studies required pursuant to the appropriate small generator interconnection process described in subdivision B 3; and <a id="paragraph-281083" class="section-permalink" href="https://vacode.org/56-594.2/#C5"><i class="fa fa-link"/></a></p></section>
						<section id="C6" class="indent-1"><p><span class="prefix-number">6.</span> Shall bill its expenses, at cost, for any additional engineering studies that a <span class="dictionary">small agricultural generator</span> is required to pay prior to interconnection. <a id="paragraph-281084" class="section-permalink" href="https://vacode.org/56-594.2/#C6"><i class="fa fa-link"/></a></p></section></text><history>2017, cc. 565, 581; 2021, Sp. Sess. I, c. 266.</history><metadata></metadata></law>