<law><site_title>Virginia Decoded</site_title><site_url>https://vacode.org</site_url><law_id>80765</law_id><section_number>56-596.6</section_number><catch_line>Distribution cost sharing program</catch_line><edition url="https://vacode.org/2025/" slug="2025" current="TRUE" last_updated="">2025</edition><structure><unit label="title" level="1" order_by="1" identifier="56">Public Service Companies</unit><unit label="chapter" level="2" order_by="1" identifier="23">Virginia Electric Utility Regulation Act</unit></structure><text>
						<section id="A"><p><span class="prefix-number">A.</span> As used in this section:
			&#x201C;<span class="dictionary">Hosting capacity</span>&#x201D; means the amount of aggregate generation that can be accommodated on the electric distribution system without any infrastructure upgrades.
			&#x201C;<span class="dictionary">Program</span>&#x201D; means the distribution cost sharing <span class="dictionary">program</span> established pursuant to this section.
			&#x201C;<span class="dictionary">Qualifying upgrade</span>&#x201D; means a system upgrade that increases the <span class="dictionary">hosting capacity</span> of the utility&#x2019;s distribution system.
			&#x201C;<span class="dictionary">Sharing project</span>&#x201D; means any distributed energy resource with an alternating current (AC) nameplate capacity rating greater than or equal to 250 kilowatts and less than or equal to three megawatts within the Phase I or Phase II Utility&#x2019;s service territory seeking to interconnect to the utility&#x2019;s distribution system and participate in net energy metering pursuant to &#xA7; <a class="law" title="Net energy metering provisions" href="/56-594/">56-594</a> that utilizes distribution system upgrades that were necessary to interconnect a <span class="dictionary">triggering project</span>.
			&#x201C;<span class="dictionary">Triggering project</span>&#x201D; means a project application in the interconnection queue at a given substation or feeder that requires a <span class="dictionary">qualifying upgrade</span> to successfully interconnect the project to the electric distribution system. <a id="paragraph-289481" class="section-permalink" href="https://vacode.org/56-596.6/#A"><i class="fa fa-link"/></a></p></section>
						<section id="B"><p><span class="prefix-number">B.</span> The <span class="dictionary">Commission</span> shall establish by regulation a distribution cost sharing <span class="dictionary">program</span> for Phase I and Phase II Utilities, as those terms are defined in subdivision A 1 of &#xA7; <a class="law" title="Generation, distribution, and transmission rates after capped rates terminate or expire" href="/56-585.1/">56-585.1</a>, to construct distribution system upgrades required to interconnect <span class="dictionary">triggering projects</span>. Under the <span class="dictionary">program</span>, when a Phase I or Phase II Utility determines that a <span class="dictionary">qualifying upgrade</span> is required to interconnect a <span class="dictionary">triggering project</span>, such utility shall determine the costs of the <span class="dictionary">qualifying upgrade</span> and the net increase in <span class="dictionary">hosting capacity</span> that would result from the construction of the <span class="dictionary">qualifying upgrade</span>. The costs of the <span class="dictionary">qualifying upgrade</span> shall be subject to approval by the <span class="dictionary">Commission</span> that the costs are reasonable and prudent. The <span class="dictionary">program</span> shall require each Phase I and Phase II Utility to allocate the costs of <span class="dictionary">qualifying upgrades</span> among any <span class="dictionary">sharing projects</span> based on the AC nameplate capacity rating of each <span class="dictionary">sharing project</span>, except that a project shall be exempted from the <span class="dictionary">program</span> if the owner or developer of such project elects to pay in full the approved cost of any associated <span class="dictionary">qualifying upgrade</span>. The <span class="dictionary">Commission</span> shall determine limits on cost recovery for ratepayers and the appropriate time period for cost recovery under the <span class="dictionary">program</span>. The <span class="dictionary">program</span> shall also require that the costs attributed to jurisdictional <span class="dictionary">triggering projects</span> are recovered from jurisdictional <span class="dictionary">sharing projects</span> and costs attributed to nonjurisdictional <span class="dictionary">triggering projects</span> are recovered from nonjurisdictional <span class="dictionary">sharing projects</span>. The <span class="dictionary">Commission</span> may establish a system to refund projects for any interconnection upgrade costs collected during time periods in which such projects are not operational and may provide such refunds upon the <span class="dictionary">petition</span> of the owner of a participating project. <a id="paragraph-289482" class="section-permalink" href="https://vacode.org/56-596.6/#B"><i class="fa fa-link"/></a></p></section></text><history>2025, cc. 615, 658.</history><metadata></metadata></law>