§ 62.1-44.15:26.1 Termination of Construction General Permit coverage

A. A VSMP authority shall recommend that the Department of Environmental Quality terminate coverage under a General Permit for Discharges of Stormwater from Construction Activities (Construction General Permit) within 60 days of receiving a complete notice of termination from the operator of the construction activity.

B. Coverage under a Construction General Permit shall be deemed to be terminated 90 days after the receipt by the VSMP authority of a complete notice of termination from the operator of the construction activity.

C. If a VSMP authority receives a notice of termination of a Construction General Permit that it determines to be incomplete, the VSMP authority shall, within a reasonable time, inform the operator of the construction activity of such incompleteness and provide the operator with a detailed list itemizing the elements of information that are missing from the notice.

History

This law was first created in 2018. The record of its establishment is cataloged in chapter 630 of that year’s edition of “Acts of Assembly,” the annual state publication listing all changes made to the Code of Virginia in that year.

2018, c. 630.